Project Title: Energy Efficiency Improvements to Kis Bt.’s Buildings Using Renewable Energy
Project Identification Number: VEKOP-5.1.1-5-1-2-16-2019-00141
Grant Amount: HUF 11,599,287
Project Start Date: 19 March 2019
Project Description
The project involved energy efficiency improvements to two buildings at Natura Hill, a tourism and hospitality establishment. The renovation included the complete external thermal insulation of the event building, which serves as a community space, along with the replacement of windows and doors. The heating system was also modernised, and an air-to-water heat pump system was installed to provide heating during the colder months and cooling during the summer.
A solar photovoltaic system was installed at the guesthouse. The energy efficiency improvements are expected to reduce annual greenhouse gas emissions by 9.08 tonnes of CO₂ equivalent.
As part of the project preparation, energy performance certificates were prepared for both buildings, covering their existing and planned conditions. Structural engineering assessments were also carried out to evaluate the stability of the buildings.
Main Elements of the Project
1. Installation of a Solar Photovoltaic System
A solar photovoltaic system with a total capacity of 56.65 kW was installed on the structurally suitable roofs of the buildings. The system consists of 206 solar panels and three three-phase inverters with a combined rated capacity of 25 kW.
The installed solar energy system is expected to cover more than 90% of the combined electricity demand of the two buildings following the improvements.
2. Comprehensive Energy Efficiency Renovation of the Event Building
The event building underwent a complete energy efficiency renovation, including external thermal insulation and the replacement of windows and doors. These improvements enhance the building’s thermal performance and significantly reduce heat loss.
The modernisation of the heating and cooling systems, together with the installation of an air-to-water heat pump, provides further substantial improvements in energy efficiency.
Project Completion Date: 28 September 2020
Funding Rate: 44.9%